construction progress

  • Excavation works are 100% completed in Zones, B1’ B2’ B10’ B1 till B10 & BK
  • Concrete works are in progress in buildings A03 to A06 A16 to A19 A27 to A3, A’01 to A’04 B05 to B08 B10 B11 C02 to C04 D01 D02 D12 E03 to E07 G01 to G04 &block H
  • Concrete works are 100% completed in 34 buildings A07 to A15 A 21 to A26 B04 C01 D03 to D14 E08 to E09 F01 to F05
  • Masonry, plaster & MEP embedded works are in progress in buildings A24 to A26 B04 D03 D04 D09 to D14 E05 to E07
  • Masonry, MEP 1st fix and plaster works are 100% completed in buildings A07 to A10 A12 to A15 A21 to A23 A25 C01 D05 to D08 E08 E09 F01 to F05
  • Painting works are in progress in buildings A07 to A10 A25 A26 B04 C01 D07 D08 F03
  • Ceramic tiling works are in progress in buildings A07 to A10 A26 C01 D07 D08
  • Facade external cladding works are in progress in buildings A07 A10 A24 A25